PROJECT MANAGER UPDATE
This week
- Continued works along The Throughfare between Swan Lane to Bullock Fair Close.
- Swan Lane to Bullock Fair Close works – Continued installation of new paving slabs and new
drainage features up to Bullock Fair Close. - Electrical disconnection works, removal of bollards and new electrical supply works to be
completed by Amey at traffic island at The Thoroughfare / Redenhall Road. - PIN letter to be issued for carriageway resurfacing works taking place from 4th Dec – 9th Dec.
Next week
- Swan Lane to Bullock Fair Close works – Continuation of drainage works at Bullock Fair Close.
- Installation of tactile paving on crossing points along The Thoroughfare.
- Works at traffic island at The Thoroughfare / Redenhall Road. Removal of paving, kerbs and
excavation works.