Town Centre Project – Update 18 November 2022

PROJECT MANAGER UPDATE

This week

  • Continued works along The Throughfare between Swan Lane to Bullock Fair Close.
  • Swan Lane to Bullock Fair Close works – Continued installation of new paving slabs and new
    drainage features up to Bullock Fair Close.
  •  Electrical disconnection works, removal of bollards and new electrical supply works to be
    completed by Amey at traffic island at The Thoroughfare / Redenhall Road.
  • PIN letter to be issued for carriageway resurfacing works taking place from 4th Dec – 9th Dec.

Next week 

  •  Swan Lane to Bullock Fair Close works – Continuation of drainage works at Bullock Fair Close.
  • Installation of tactile paving on crossing points along The Thoroughfare.
  • Works at traffic island at The Thoroughfare / Redenhall Road. Removal of paving, kerbs and
    excavation works.

Questions – All public correspondence should be addressed to: enquiries@harleston-tc.gov.uk.  We will answer those questions where we have the relevant information.  We have been advised to forward questions which we are unable to answer to the project team, who commit to a response within 10 days.