Project Manager Update
This week – w/c 28th Nov
- Installation of tactile paving at crossing points along The Thoroughfare.
- Installation of blue brick delineations by Tudor Bake House.
Next week – w/c 5th Dec
Carriageway resurfacing works along The Thoroughfare.
Works to commence on Sunday 4th December as broken down below:
- Sunday 4th – Plane of existing surface & preparation works for carriageway resurfacing works area.
- Monday 5th / Tuesday 6th – Adjustment & replacement works to existing ironwork prior to surfacing works;
- Wednesday 7th December – Carriageway surfacing works; &
- Thursday 8th / 9th Friday – Lining works for all road markings in resurfacing works area.
The works above are all subject to the weather conditions at the time.
Questions – All public correspondence should be addressed to: enquiries@harleston-tc.gov.uk. We will answer those questions where we have the relevant information. We have been advised to forward questions which we are unable to answer to the project team, who commit to a response within 10 days.