Town Centre Update – 9 December 2022

Project Manager Update

This week – w/c 5th Dec

  • All footway paving works complete, with some sections required sanding and sealing in certain locations. This is to be completed by the end of the week subject to weather conditions.
  • Carriageway resurfacing works along The Thoroughfare are ongoing – Planning and ironwork adjustment / replacement works have been completed. The majority of new carriageway surfacing has been completed, with 3 junctions due to be completed on 08/12.
  • New road markings due to be installed over the course of 08/12 & 09/12, subject to weather conditions.
  • Removal of TM on site subject to works above being completed.

Next week – w/c 12th Dec

  • Repairs made to Town Centre sign on Market Place.
  • Site compound clearance to begin, expected completion by end of the week.
  • Snagging works to be identified and completed where possible.

Questions – All public correspondence should be addressed to: enquiries@harleston-tc.gov.uk.  We will answer those questions where we have the relevant information.  We have been advised to forward questions which we are unable to answer to the project team, who commit to a response within 10 days.