Town Centre Update – 12 December 2022

Project Manager Update

This week – w/c 12th Dec

  • Repairs made to Town Centre sign on Market Place.
  • Site compound clearance to begin, expected completion by end of the week.
  • Snagging works to be identified and completed where possible.

Some service covers need adjusting following the carriageway surfacing works. These are anticipated to be completed on Tuesday 13th December.

The traffic management measures along The Thoroughfare will remain in place to allow for carriageway surfacing snagging works to be carried out in the early part of the week.

These are due to be completed by Wednesday at the latest.

All traffic management will be removed from the site as soon as possible upon completion of the snagging works.

Site operatives will continue to be located at the closure points to accommodate deliveries to businesses.